What is BIM (Building Information Modeling)?
BIM (Building Information Modeling) is a way of designing, building and running a building with one shared digital model. The model shows the building in 3D. It also stores information about each part, such as its material, size, cost and performance.
All project teams work from coordinated, federated models rather than disconnected 2D drawings. They will use it from the first design, through construction and into daily operation.
BIM is a process, not a single program. Teams create BIM models in authoring software such as Revit, Archicad or Tekla.
How does BIM work?
The main difference to traditional drawings is in the objects. In a CAD drawing, a wall is just two lines. In a BIM model, a wall is an object with its own information - including height, layers, fire rating and the rooms on either side.
All plans, sections and schedules are generated from the model. When someone changes the wall, all of these views update automatically.
The four steps of a BIM workflow
Most BIM projects follow the same four steps.
01
Model. Each discipline builds its own model. These are usually architecture, structure and MEP (mechanical, electrical and plumbing).
02
Combine and coordinate. The discipline models are combined in a common data environment (CDE). Software then checks them for clashes, such as a duct running through a beam. The team fixes the clash in the model instead of on site.
03
Use the information. The model produces drawings, quantity take-offs and cost estimates.
04
Hand over and operate. At the end of the project, the owner receives the model and its asset data. Facility teams use it for maintenance, space planning and future renovations.
What is the difference between BIM and CAD?
CAD produces drawings. BIM produces a model that holds the project’s information. The table shows the main differences.
| CAD | BIM | |
|---|---|---|
| What gets created | 2D drawings or 3D shapes | A model made of objects with data |
| When something changes | Manual updates required | All views update from the model automatically |
| Information stored | Lines, shapes and notes | Geometry plus materials, cost and performance |
| Collaboration | Each discipline shares its own files | All disciplines coordinate in one model |
| Used for | Mainly design and documentation | Design, construction and operation |
What are the benefits of BIM?
Most benefits come from the same source. Everyone works with the same, up-to-date information.
- Fewer errors on site. Clashes are found and fixed in the model.
- Faster reviews. All parties look at the same model.
- More reliable planning. Quantities, schedules and costs come straight from the model.
- Easier communication. A 3D view is easier to understand than a set of plans, especially for non-specialists.
- Better data after handover. Facility managers receive structured information about every asset.
What are the challenges of BIM?
Here are a few common challenges most team encounter with BIM:
- Upfront costs for software and training.
- Tools from different vendors don’t always exchange data cleanly.
- Firms that work together need to agree on shared standards.
Most projects handle this with a BIM Execution Plan (BEP). The BEP is agreed at the start of the project. It defines who does what, which file formats are used and how detailed the model needs to be.
How is BIM used for existing buildings?
Most buildings were built before BIM existed. Their original drawings are often missing or out of date. This is a problem for renovation, retrofit or expansion, because the new design has to start from what is really there.
Scan-to-BIM solves this problem. It turns a measured record of the building into a BIM model.
How Scan-to-BIM works
Scan-to-BIM in three steps
| Step | What happens |
|---|---|
| 1. Capture | Laser scanners record the building. Terrestrial scanners, mobile mapping systems or both produce a point cloud, millions of measured 3D points of the current state. |
| 2. Register and check | Scans are aligned in one coordinate system and checked against control points for accuracy. |
| 3. Model | BIM specialists trace walls, floors, structure and MEP from the point cloud into BIM objects. |
The result is an as-built model. It gives designers and owners a reliable starting point and fewer surprises once work begins.
How much detail does the model need?
This depends on what the model is used for. A model for space planning needs much less detail than a model for prefabrication. The amount of detail is usually described as the level of detail (LOD).
| Use case | Detail needed | Typical LOD |
|---|---|---|
| Space planning | Low | LOD 100, or LOD 200 |
| Renovation design | Medium | LOD 300 |
| MEP coordination | High | LOD 350 |
| Prefabrication | Very high | LOD 400 |
The capture method should match the target LOD. Both are usually set in the BIM Execution Plan.